By any chance is anyone proficient with the EPA's guidelines for NPDES? I need to provide an erosion control plan for a 3 acre project site. I will include the usual silt fence around the property and tracking device at the entrance. However, we are going for a LEED certification, and need to provide extra protection for the site. I have an idea what I may need (turbidity barrier at existing outfall pipe into canal, temp. fencing around existing trees to remain, etc.) but have not been able to find where this is documented in the rules. Any direction in this is appreciated.