MyCupboard
Structural
- Aug 23, 2022
- 36
I'm looking for some guidance as to what limitations, or design strategies you all use for multiple sleeve penetrations in a concrete fdn wall. Typically, we have a detail that puts some extra bars around it to prevent cracking and to transfer the load around the hole. But for this project, i have concrete walls, varying 11' to 13' tall, that are 16" thick and they have approximately (50) penetrations (spread out over 5 different walls) that vary from 2" to 5". most of them they are requesting to be horizontally aligned and 12" apart from each other.
At first, my boss and I were thinking, why can't they just run their penetrations up through the slab. But then figured we would try to come up with a solution for the wall penetrations as they requested. Then we were considering asking them to align them vertically (or at least some of them vertically) instead of aligning 10-12 holes horizontally at 12" o.c.
I have had trouble finding any guidelines or calculations or codes regarding multiple holes so close together. Not sure if i'm overthinking it, or on the flip side if this is a major issue.
At first, my boss and I were thinking, why can't they just run their penetrations up through the slab. But then figured we would try to come up with a solution for the wall penetrations as they requested. Then we were considering asking them to align them vertically (or at least some of them vertically) instead of aligning 10-12 holes horizontally at 12" o.c.
I have had trouble finding any guidelines or calculations or codes regarding multiple holes so close together. Not sure if i'm overthinking it, or on the flip side if this is a major issue.