Is there any way to change the timescale for a chart down to minutes or even seconds?
 
Right click on the time scale when you are in Gantt chart view. Click on timescale.

Select the tier you want. click on the units drop down box, then select the unit you want: quarterly, monthly, weekly, hourly, minutes.

That should do it.

Thanks,
 
Thanks. So minutes is the lowest you can break the timescale down too, correct?
 