Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

MS Project 2010 Resource displaying on Gantt Report

Status
Not open for further replies.

Hamishk

Mechanical
May 18, 2011
2
In MS Project 2010. How do I turn on/off the display of Resources Allocated to Tasks in the Gantt Reports. Thanks a Lot.
 
Replies continue below

Recommended for you

Thank You for your help I am referring to the resource name label attached to each Task bar.

Regards Hamishk
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor