i'm creating a schedule in project.....and i have the following question: (ps. i'm very new at this)

how do i indicate the predecessor if i have a "task" C that can be started when 'either' task A or task B is completed?


thank you
 
Create Linkages between Both task A and B and Task C.

Which every task out of A and B is later will determin the starting date of Task C.