Riggspsk
Electrical
- Jul 25, 2006
- 1
I'm currently working at a site that was inactive for the last 4 years. In their great wisdom, the last contractor to leave site left all the electric motors out in a shed out back.
The site owner wants to test the motors intergrity before coupling. His question to me was, "Is there any rule of thumb on this?" and goes on to explain that he wants to know if there are any HP ranges that should be tested and for how long. Such as 50-100 hp motors need to be tested for 2 hours.
Motors are all 3-phase, some are 480, some are 4160V.
Does anyone have any expereince with this, so at least I can go in the right direction?
The warrentys on these motors have long since expired and they want to do all the work on site. We have motors from 1-300 HP, the site is a power plant.
Thanks in advance to anyone who can help out!!!
The site owner wants to test the motors intergrity before coupling. His question to me was, "Is there any rule of thumb on this?" and goes on to explain that he wants to know if there are any HP ranges that should be tested and for how long. Such as 50-100 hp motors need to be tested for 2 hours.
Motors are all 3-phase, some are 480, some are 4160V.
Does anyone have any expereince with this, so at least I can go in the right direction?
The warrentys on these motors have long since expired and they want to do all the work on site. We have motors from 1-300 HP, the site is a power plant.
Thanks in advance to anyone who can help out!!!