Jul 26, 2005 #1 juststo Materials Jul 26, 2004 3 US I am using project and trying to sum figures in a column to get a month end total. Is there any way to calculate a number of tasks vertically in project?
I am using project and trying to sum figures in a column to get a month end total. Is there any way to calculate a number of tasks vertically in project?
Jul 26, 2005 #2 IRstuff Aerospace Jun 3, 2002 44,394 US Summary tasks are used for that Otherwise, you can switch to Task Usage or Resource Usage tables for that information TTFN Upvote 0 Downvote
Summary tasks are used for that Otherwise, you can switch to Task Usage or Resource Usage tables for that information TTFN