Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Mismatch between duration total and sum of indivual duration totals

Status
Not open for further replies.

lavaghman

Computer
Joined
Jun 12, 2007
Messages
4
Location
AU
Hi there

Please see the attached screenshot. Have a mismatch between duration total and sum of indivual duration totals.

Under Tools -> Change Working Times and in Options - I have changed the hrs per day to be 7.5 and the hrs per week to be 37.5.

Any help appriciated.
Thanks,
John
 
The actual sheet would be more useful than a picture.

Did you enter the individual durations AFTER or BEFORE you made the working time change?

TTFN

FAQ731-376
 
The summary task duration is reflecting the duration (from the beginning of the subtasks to the end of the subtasks) for it's members. These tasks must be linked or the summary task would reflect 1 day. What is being shown here is the actual duration it will take to complete this summary group. Look at the beginning and ending times - this is where the fraction of a day comes from.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top