I am proposing a axially-loaded 30-inch diameter drilled shaft adjacent to a tunnel wall. The drilled shaft is designed for end bearing of 5 tsf. The length of the drilled shaft will be 50 feet. The bottom of the tunnel is at a depth of 40 feet and the height of the arched tunnel is 10 feet. The tunnel wall is composed of unreinforced concrete constructed in 1906 (i.e., fragile eggshell).
In reality, the loading of the drilled shaft will include side friction and end bearing with more side friction after construction and shifting to end bearing over time.
What is the minimum clearance of the drilled shaft from the tunnel so that zero stress from side friction is imposed on the tunnel wall?
Thanks for reading.
PS: Not considering bond break since extra cost.
In reality, the loading of the drilled shaft will include side friction and end bearing with more side friction after construction and shifting to end bearing over time.
What is the minimum clearance of the drilled shaft from the tunnel so that zero stress from side friction is imposed on the tunnel wall?
Thanks for reading.
PS: Not considering bond break since extra cost.