Jruggi
Civil/Environmental
- May 7, 2007
- 1
I have a concrete pad, reinforced and 15" thick, it has been specified a min of 4500 psi, however I have been supplied the 5 day test breaks (reaching 3300 to 3500 psi) and asked can this support an 18 wheeler loaded (80,000#) can drive on this at day 5 and day 6. I have declined but told to "research it more" so the question is, is this something that can be achieved or steer clear of and wait.