Flow : 800 l/sec
Diam : 700 mm
field conditions :underground, 2 m ,watertable 1 m over the t.o.p.
pressure class : PN 6
I will develop a detail study, and I only need a first aproach costs /ratios
Best regards,
SPLIT
If you need more information, please make me know it.