Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TugboatEng on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

microsoft project 1

Status
Not open for further replies.

pitulafresca

Petroleum
Joined
Jun 18, 2003
Messages
4
Location
IT
given a very short activity ,how can I set it so that I can spread it over a very long period?
An example is probably more explanatory:
I have an activity that starts now and ends in one month time. The activity requires only 3 hours work for a project engineer and 10 hours for the draft man. I want to assign the resources but this changes the activity work amount despite having ticked the effort driven option.
Can anybody help me?
thanks
 
You could simply load the resource with less than 100% effort. The PE would be loaded as PE[7.5%] and the DM loaded as DM[25%].

Note that Project will round 7.5% up to 8%.

TTFN
 
Hello. First of all make this a fixed duration task. After you have assigned the resources to the task, then go to the Task Usage view and you can specify exactly how many hours each resource will be assigned for this task.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top