I am designing a mat slab which will support mechanical equipment such that the differential settlement between the edges of the 115ft x 15 ft may cannot be more than 0.002 in. Have gone upto 48" concrete mat, still getting differential settlement. Thought someone may have experience in how to get rid of differential settlement?
Thanks in advance for helping comments.
I am designing a mat slab which will support mechanical equipment such that the differential settlement between the edges of the 115ft x 15 ft may cannot be more than 0.002 in. Have gone upto 48" concrete mat, still getting differential settlement. Thought someone may have experience in how to get rid of differential settlement?