noobrich
Structural
- Sep 15, 2009
- 1
I am working at a nuclear facility. Our group has changed some components on a large crane. As a result of this change we are planning to load test the crane to 125%. An engineer has challenged stating that we must complete an analysis to verify the structure is able to support the increased load. He is indicating that we have to check the structure for side load perpndicular crane.
In my experience the load test is simply completed. Further buiding analysis is not required.
I would argue that the original design utlises a live load factor of 1.5. This is controlled activity below this limit. For this reason it is acceptable to complete the test.
Please advise who is correct. Thanks for any insight.
In my experience the load test is simply completed. Further buiding analysis is not required.
I would argue that the original design utlises a live load factor of 1.5. This is controlled activity below this limit. For this reason it is acceptable to complete the test.
Please advise who is correct. Thanks for any insight.