debar99
Industrial
- Oct 10, 2005
- 1
We usually let concrete floors we produce sit for 21 days. (until the 21 day break test comes in ) We want to start construction on the floors 7 days after the pour is there any codes that permit this. I have heard that if the 7 day test is returned at 75% then there shouldn't be a problem, We are using light weight with a 3000 PSI