laff24
Structural
- Dec 7, 2005
- 4
I have 24 ft 800S162-50 ceiling joists interrupted by a 16" high linear diffuser. 4 ft from end of bearing. Which breaks the joist. It would be to expensive to add an additional drop ceiling. Has anyone faced this before. Pretty sure it needs to be a framed section. Please note the crude section will add a diagonal brace. Any other thoughts?