dadoftrips
Chemical
- Aug 23, 2003
- 2
I have a post tension slab that was incorrectly installed. I have found that the split wedges use to set the cables after tensioning were of different angles and therefore the tension in the cables were lost or non-existent from the start. The unskilled laborer just pulled out wedges out of a box of assorted wedges. I believe the issues here are QA/QC, lack of good procedures and performing a task that is atypical to the standard field worker.
My question to this forum is whether there is any technique in slab leveling that can take advantage of the post tension technology? Can existing cables be removed and new cables restrung and tensioned to pullup the slab to a uniform level in all directions? My attempt here is to save the need for the installation of piles or piers and save cost of slab leveling.
My question to this forum is whether there is any technique in slab leveling that can take advantage of the post tension technology? Can existing cables be removed and new cables restrung and tensioned to pullup the slab to a uniform level in all directions? My attempt here is to save the need for the installation of piles or piers and save cost of slab leveling.