Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Lateral load test on pile 1

Status
Not open for further replies.

StructureEnggGLM

Structural
May 20, 2017
2
Dear all,

In one of our project in Saudi Arabia, The testing agency is going to perform lateral load test on pile as per ASTM D3966. The lateral load of 160Mton (2 time design load of 80Mton) is needs to be applied on the test pile. Required weight (for coefficient of friction of 0.35) of "160Mton / 0.35 = 457 Mton" shall yield huge quantity of blocks ( for example for concrete block of 1 cum size or 2.4 Mton weight) = 457 / 2.4 = 190 nos. Is there any other option to reduce nos. of blocks required. We have 75 blocks available with us.
 
Replies continue below

Recommended for you

You could test two piles simultaneously. Check section 6.4 of ASTM D3966.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor