Im putting together a chart for bending stresses on large timbers for emergency use - Think of a building collapse, shoring etc for USAR work. Figure 7 days max duration.
For timbers 8x8 and larger, I was using a Fb=1000, and Fv=165 as generic values. How do you folks feel about those to be conservative? Cant get species specific, since in a emergency situation, will take what can be found.
Thanks
For timbers 8x8 and larger, I was using a Fb=1000, and Fv=165 as generic values. How do you folks feel about those to be conservative? Cant get species specific, since in a emergency situation, will take what can be found.