pipeeng3000
Mechanical
- Feb 15, 2008
- 4
We are looking at options for tieing in a new (>40km)pipe section that will have been laid alongside the existing liquid line. Considering that we have to remove the fluid from the old pipe section as part of the operation are there any thoughts on how line plugging might be carried out for the tie-ins of the new section??