vincentpa
Structural
- Nov 9, 2005
- 223
We have an elevated concrete slab on form deck in a large industrial building. How often do you space the control joints? How often do you space the expansion joints? Where do you locate the control and expansion joints? I imagine that the location of the joints will differ with the orientation of the infill beams. Will the spacing and location of the control joints be the same as a composite slab (beams, concrete with studs)?