blacksix
Industrial
- Dec 24, 2003
- 1
I have a jib crane that I need to mount on a portable base. By portable, I mean made of steel and concrete and not fastened to the floor. The boom is 10 ft long and the clearence is 11 ft. The capacity is 1/4 ton. How big does this base need to be, and are there any tools that can help me determine the overturn moment and how big my base needs to be. I have read in several other posts that the base must be 3-5 ft deep. I would like to have the base be no more than 1 ft deep. Please advise. Thank you.