dean427
Chemical
- Dec 5, 2010
- 24
Hi all.
I have run a quick search on the forum be couldn't find anything that covered this topic so hence the question.
Caveat...I'm a process engineer rather than mechanical so I apologize in advance for any ignorance below.
The question is...Is it safe to complete a hydrotest on an aging/"late-life" operating facility? Facility is an onshore hydrocarbon gas conditioning and processing terminal.
Background:
We have identified via a HAZOP review that a gas compressor's suction pipework may have its design pressure exceeded during a settle-out case when the compressor trips.
My Mechanical Engineering Technical Authority wishes to hydrotest this section of pipework in order to re-rate it.
I trust his experience (much more years under his belt than me) however I feel that a hydrotest being completed on a circa 40 year old gas plant is very risky - i.e. how can we assure ourselves that every mm2 of pipework has been inspected to ensure no defect which could cause the pipework to fail during the test at extremely high pressure? Not to mention trying to dry the system after the test should it be successful will be very difficult!
For info...gas plant has x2 processing modules. The intent is to complete the hydrotest during a turnaround/shutdown on one module with the second module still running (other workscopes will also be ongoing on the shutdown module) & site will be fully manned.
Is this something that is fairly routine in wider industry? My technical authority seems to be driven to do this to ensure code compliance but I feel that purposefully exposing a system to the hazard you are trying to mitigate against is not logical or sensible.
Grateful in advance for any advice or steer regarding this issue.
Thanks
Dean
I have run a quick search on the forum be couldn't find anything that covered this topic so hence the question.
Caveat...I'm a process engineer rather than mechanical so I apologize in advance for any ignorance below.
The question is...Is it safe to complete a hydrotest on an aging/"late-life" operating facility? Facility is an onshore hydrocarbon gas conditioning and processing terminal.
Background:
We have identified via a HAZOP review that a gas compressor's suction pipework may have its design pressure exceeded during a settle-out case when the compressor trips.
My Mechanical Engineering Technical Authority wishes to hydrotest this section of pipework in order to re-rate it.
I trust his experience (much more years under his belt than me) however I feel that a hydrotest being completed on a circa 40 year old gas plant is very risky - i.e. how can we assure ourselves that every mm2 of pipework has been inspected to ensure no defect which could cause the pipework to fail during the test at extremely high pressure? Not to mention trying to dry the system after the test should it be successful will be very difficult!
For info...gas plant has x2 processing modules. The intent is to complete the hydrotest during a turnaround/shutdown on one module with the second module still running (other workscopes will also be ongoing on the shutdown module) & site will be fully manned.
Is this something that is fairly routine in wider industry? My technical authority seems to be driven to do this to ensure code compliance but I feel that purposefully exposing a system to the hazard you are trying to mitigate against is not logical or sensible.
Grateful in advance for any advice or steer regarding this issue.
Thanks
Dean