Hello everyone,
I have run into multiple issues in designing Post-Tensioned Parking Structure, and hoping to get some feedback from you guys. A quick summary of the parking structure building:
- 8" PT SLAB (Slab is thicker than usual, Live load requirements (100 psf) for this building are higher than parking structures
- 14"x38" PT Beams spaced at 18' O.C.
- Some 24" wide PT girders
- 24"x24" Concrete columns
I have attached a pdf with snapshots of output from software as well as a quick hand check for prestressing force requirement.
Observations:
1) - Moments in beams are much smaller than anticipated - There is 35-40% difference between ETABS/Handcheck vs SAFE (SAFE MOMENTS SMALLER)
2)- All beams are failing - I am having to require insane amounts of Pre-stressing loads (and still failing) eventhough the moments are smaller than actual moments, this is going to get worse once I fix the moment issue.
3)- Flexure Reinforcing (non-prestressed) requirements are higher at mid span (for positive moments) than for end moments (negative), even though the end moments are larger.
Below are links to PDF results and SAFE model:
I tried messing the beam section properties in the model, by making it a T-beam and assigning it an effective width, but no effect on results. Tried without effective width (beam stem only) still no luck. Any feedback would be appreciated.
Thanks,
I have run into multiple issues in designing Post-Tensioned Parking Structure, and hoping to get some feedback from you guys. A quick summary of the parking structure building:
- 8" PT SLAB (Slab is thicker than usual, Live load requirements (100 psf) for this building are higher than parking structures
- 14"x38" PT Beams spaced at 18' O.C.
- Some 24" wide PT girders
- 24"x24" Concrete columns
I have attached a pdf with snapshots of output from software as well as a quick hand check for prestressing force requirement.
Observations:
1) - Moments in beams are much smaller than anticipated - There is 35-40% difference between ETABS/Handcheck vs SAFE (SAFE MOMENTS SMALLER)
2)- All beams are failing - I am having to require insane amounts of Pre-stressing loads (and still failing) eventhough the moments are smaller than actual moments, this is going to get worse once I fix the moment issue.
3)- Flexure Reinforcing (non-prestressed) requirements are higher at mid span (for positive moments) than for end moments (negative), even though the end moments are larger.
Below are links to PDF results and SAFE model:
I tried messing the beam section properties in the model, by making it a T-beam and assigning it an effective width, but no effect on results. Tried without effective width (beam stem only) still no luck. Any feedback would be appreciated.
Thanks,