brandnew1
Aerospace
- Apr 9, 2010
- 73
i believe i have this interpretation, but i wanted to run this by all of you just to make sure i'm on solid ground.
When i think of true position i think about the formula:
True Position = 2? Deviation in X² + Deviation in Y² and i think of this in terms of diametrical situations.
Per the attached pdf, the .010 true position to datum B doesn't appear to be a diameter. So will this be a straight .010 plus or minus value for each side alone?
Thank you
When i think of true position i think about the formula:
True Position = 2? Deviation in X² + Deviation in Y² and i think of this in terms of diametrical situations.
Per the attached pdf, the .010 true position to datum B doesn't appear to be a diameter. So will this be a straight .010 plus or minus value for each side alone?
Thank you