Please can somebody answer in my question.
In old substations 400/220kV we had by the switch gears (disconector, earthing switch,circuit breaker) wire interlockings. We have now in implimentation 400/110kV new substation, but the contractor (I dont want to say the company name) give as the drawings and there are only logical interlocks, but no wire (electrical) interlocks. I ask for help: From your exprience It's enough only logical interlocks or there must be and electrical interlocks.
With respect
G.Kabashi .
In old substations 400/220kV we had by the switch gears (disconector, earthing switch,circuit breaker) wire interlockings. We have now in implimentation 400/110kV new substation, but the contractor (I dont want to say the company name) give as the drawings and there are only logical interlocks, but no wire (electrical) interlocks. I ask for help: From your exprience It's enough only logical interlocks or there must be and electrical interlocks.
With respect
G.Kabashi .