lgoolsby
Industrial
- Jun 20, 2003
- 1
I am planning to build a house using the Insulated Concrete Forms (ICF). The building inspector is unfamiliar with this and is thus being very difficult. The plan code for MI says that if the wall dimensions are more than 40' or 60' the plans may need the sign or seal of the architect or engineer. I had the plans re-drawn by the ICF company architects. Now he wants a MI engineer to approve and seal the documents. Of course these walls are just like any other poured concrete, the forms just stay in place. HELP. Any advice or suggestions?