You are creating a maintenance nightmare.
Image at some future date, plant personnel attempting to 'walk down' a specific line to add a new tap or branch connection. Nearly impossible. We have all walked down a line in a plant when the lines are individually insulated. At some plants it is still nearly impossible to completely 'walk down' a line when the headers are located in a large pipe rack.
Also, imagine if one(1) of the lines leak for any reason (i.e. gasket joint). The fluid would not be contained to any one location and identifying the source of the leak nearly impossible.
In addition, how would the plant add a line(s) at some future date.