Is there any way to justify to the customer the use of a 2" long weld neck as an inspection opening on a 24" OD vessel? This design slipped through the cracks. It is built & installed on the skid. It would be very costly at this point to repair. The local jurisdiction & the AI will accept this vessel as a one time build. However, the customer wants some clarification. I would appreciate any comments.
Thank you
Is there any way to justify to the customer the use of a 2" long weld neck as an inspection opening on a 24" OD vessel? This design slipped through the cracks. It is built & installed on the skid. It would be very costly at this point to repair. The local jurisdiction & the AI will accept this vessel as a one time build. However, the customer wants some clarification. I would appreciate any comments.