Hi, dredging up this thread I just came across, I need to fill in several CMU walls for architectural reasons (typically about 10'x10' openings in a 27' tall 8" CMU grouted wall). My question is: what is the actual procedure to tie the new in-fill wall in at all four sides (or do you not tie into the top?).
I don't know if I'm lacking imagination or if this is really tricky to do. I can see embedding bond beam bars each side, and vertical bars into my footing, but how do you slide blocks in and still tie steel to the bottom course of the existing lintel above?
Do I not need to bother with that, considering this will not be a shear wall? Still, how do I grout cells and finish the top course? Any pointing in the right direction would be appreciated.