To maximize the full advantages of any NDT, it must remove unacceptable materials from the production stream as soon as possible. However, everything in life must consider the economic factors. It would be nice to utilize volumetric NDT at every stage of manufacturing, but it would be cost prohibitive.
Codes and standards specify the minimum level of NDT required. It may not be the optimum level of NDT; it is simply the minimum level of NDT required. It is good business for a manufacturer to institute a NDT system that utilizes resources wisely to maximize the profits earned on any single item produced. It the cost of materials and labor to manufacture a widget is low, the cost of expensive volumetric NDT is not cost effective. However, as the cost in time, materials, and labor increases, it becomes more cost effective to introduce various levels of NDT during production. Back to the basic concept of why invest time, money, and labor into a part that is not acceptable?
I had a project several years ago where I was called in by a client to perform a final inspection of a component that cost many thousands of dollars. I was called in because the client's engineer saw something that "didn't look right." The problem was the manufacturer failed to have complete fusion in the root bead of a groove weld. The incomplete fusion was only discovered when the completed weldment was heat treated and machined to very cloes tolerances. The bottom line was that there was no way to repair the deficient weld and still hold the tolerances required by the design. The unit was scrapped and a new one constructed. Again the same problem was identified after all construction, PWHT, and machining was completed. I suggested to the manufacturer that some in-process NDT, i.e., MT, be performed on the component that was causing the problem. I asked the manufacture how much time, material, and labor were invested in the component while it was on the bench being welded.
The manufacturer stated that it was worth about $50. I pointed out that at that stage, if a problem was identified, it could be easily repaired for minimal cost. His reply was that it was not required by the contract and he refused to do it.
Another unit was manufactured and it was rejected for the same reason as the first two units. Incomplete fusion in the root bead. I suggested that the welders be trained to use MT to inspect the root when they back gouged the groove. It inspection was not a required inspection, no report was required, the welder did not need to be certified to perform the in-process inspection.
Again the manufacture refused and another unit was manufactured and rejected at the final (required) inspection. Once again I made my suggestion and stated that the manufacture had produced several units at a cost of many thousands of dollars and not one was acceptable and in each case the cause of the problem was the same component. Finally he was in agreement that something had to be done before the company went broke. It was only after scrapping several completed units and the recognition that the manufacturer had lost nearly a million dollars were they receptive to in-process NDT. Sometimes there is no cure for "stupid".
Once in-process NDT was instituted at a cost of less than $25 per unit, there were no more rejects during the final inspection.
Best regards - Al