May 7, 2004 #1 Verner Mining Joined Jul 7, 2003 Messages 24 Location US I am finding that when I import a baseline from one schedule to another, I lose the baseline (bars) but the CPI and SPI values still remain correct. How do I keep the baseline from the imported schedule?
I am finding that when I import a baseline from one schedule to another, I lose the baseline (bars) but the CPI and SPI values still remain correct. How do I keep the baseline from the imported schedule?