cuky2000
Electrical
- Aug 18, 2001
- 2,135
A 345 kV switchyard was energized successfully while ago. For more than 3 months, the operating voltage of 368 kV RMS marginally exceed the system maximum rated voltage of 362 kV RMS. The system and equipment are also rated for 1300 kV crest BIL and 900 kV crest switching surge.
There is not indication of damage so far.
QUESTIONS:
a) What will be the long term impact exceeding this rating from the technical stand point?
b) There is any guideline or publication to determine if the BIL or switching surge is the dominant factor for rating the equipment and system?
c) Should the short circuit rated of 40 kA be derated for higher operating voltage?
Thanks in advance for your input.
There is not indication of damage so far.
QUESTIONS:
a) What will be the long term impact exceeding this rating from the technical stand point?
b) There is any guideline or publication to determine if the BIL or switching surge is the dominant factor for rating the equipment and system?
c) Should the short circuit rated of 40 kA be derated for higher operating voltage?
Thanks in advance for your input.