By saying "out performed", I was referring to the entire effort including the presentation that had to addresss the intent and specifics required for the proposal. - Some may use the term "out sold", but the early completion is part of the total performance package.
Before the proposal due date, the winning consortium meet with many local groups because of the logistics and traffic. After the project started, they had site tours regularly and every engineering and construction group around was at the site at least once where the construction people and design people were available. The proposal even included options on the color of the bridge and the shape of the piers since the site is very visable.
The early completion was due to a number of factors.
1. The contractor secured an area near one end of the bridge to construct a heated shelter to start making the concrete elements in February, virtually on site and only had to haul the others to the opposite side of the river over an adjacent bridge at night. It was vitually an on-site precast plant near the ready-mix plant.
2. The spring and summer weather was good and the contractor used a lot of overtime (24x7) to take advantage of that. This permitted the on-site finishing concrete to go in early and not encounter the typicial weather problems possible in October, Novemeber and December. Concrete temperature and curing was not a problem. A few years ago, the area got 28" of snow in October.
3. The bridge was basically built on a solid, known limestone foundation.
4. Because of the locations of the I35W exit ramps north and south of the bridge, traffic ended up being diverted well around the actual construction area.
MNDOT did a good job of adding temporary lanes to several roads and divert the traffic around the area without total jam-ups, but over-all travel times were definitely increased. The trucks using I35 were forced to use alternate routes or take the loop freeway, which caused some problems 10 to 20 miles away. Unfortunately, the sister route to I35W is I35E that goes through St. Paul and a portion is limted to 45 mph and trucks are not permitted and it is called a "boulevard", although many people refer to it as a "learners freeway". The time, traffic delays, extra mileage were all a part of the the formula that provided the big completion bonus (half of the extra cost to the community).
Because of the disaster, there was a big inspection effort made in Minnesota on all bridges. Many problems were found, at least one major bridge is being replaced and several replacement dates were moved up significantly and the inspection procedures have been revised, so there was a silver lining in part of the black cloud. Since most of the problems found related to steel, the choice of concrete was generally approved by the public after the actual contract award. No one complained that the project was completed early.
It was an interesting project to observe. It was a good job of selling, engineering, construction and public relations. I assume the engineering was sound, since the firms have built many bridges around the country. It is not my place to check the designs even if I was a bridge inspector at one time in my past life before I was registered.