tlewis
Mechanical
- Dec 27, 2003
- 6
I have a 10" 150 psig steam line that runs between two boilers on a large university campus (transfer line). One section of the pipe midway between the boilers is in a walkable tunnel. The pipe enters the west wall of the tunnel, turns north for 60' then then turns east and exits the east wall. We plan to cut an elbow (turning east) and install a "tee" to run a new 10" line down the tunnel to the north. The university wants to take only a minimal (24 - 48 hr) shutdown to cut the elbow and install the tee, which is feasible with a pre fab tee, but my concern is the pressure boundary of the hydrostatic test.
Relative to the tee, there are three boundaries for the pressure test:
1) NORTH: this will be a new north isolation valve on the north end of the tee. New 10" piping will run north of the tee, and we will pressure test it after the tee is installed.
2) EAST: when we cut the elbow, the east side of the tee will be connected to existing pipe with an existing east isolation valve within 3 feet.
3) SOUTH: will cut the other end of the elbow, and install tee with new south isolation valve. HOWEVER, the new weld on the other (south) side of the new south valve in the existing pipe will be outside the boundary established by the new south & north valves and the existing east valve. To make things worse, there is no isolation valve in the 10" line from the tunnel back to the steam boiler (well over 1,000+ feet).
So the quesion is: if you have a new weld in a 150 psig steam line 5' away from an isolation valve and over 1,000' away from the other isolation valve, how would one pressure test the new weld? Hydro test seems impossible due to length and short shutdown duration. Pneumatic also seems impossible, and possibly dangerous. Do pipefitters have an inflatable "pig" that can be placed in the pipe for the hydrotest, and then deflated and pulled out later?
Any ideas or input appreciated!
Relative to the tee, there are three boundaries for the pressure test:
1) NORTH: this will be a new north isolation valve on the north end of the tee. New 10" piping will run north of the tee, and we will pressure test it after the tee is installed.
2) EAST: when we cut the elbow, the east side of the tee will be connected to existing pipe with an existing east isolation valve within 3 feet.
3) SOUTH: will cut the other end of the elbow, and install tee with new south isolation valve. HOWEVER, the new weld on the other (south) side of the new south valve in the existing pipe will be outside the boundary established by the new south & north valves and the existing east valve. To make things worse, there is no isolation valve in the 10" line from the tunnel back to the steam boiler (well over 1,000+ feet).
So the quesion is: if you have a new weld in a 150 psig steam line 5' away from an isolation valve and over 1,000' away from the other isolation valve, how would one pressure test the new weld? Hydro test seems impossible due to length and short shutdown duration. Pneumatic also seems impossible, and possibly dangerous. Do pipefitters have an inflatable "pig" that can be placed in the pipe for the hydrotest, and then deflated and pulled out later?
Any ideas or input appreciated!