John_187
Mechanical
- Apr 21, 2018
- 68
There is a project where the contractor is asking if he can pressure test the potable water piping system with dry nitrogen instead of water. The reason this was asked is because "it would will be very difficult to get the air out of the pipe if water test is done". The pressure test is to be 125 psig for 1 hour. Is this acceptable and/or common practice? Thanks