lganga
Mechanical
- Apr 10, 2011
- 109
Dear colleagues
I have to deal with the job of joining the upper part of a heavy vessel by welding and PWHT.
I have reclaim the construction company, the procedure to suport this upper part during heat treatment.
This upper part is 60 mm- SA 516 70 carbon steel plate
Their answer, was to hold it with a crane (600 tons.). I have refused this procedure for holding the part, due to lack o plumbness and relative movements that induce cracks during the process.
I have already done this job in shorter and lighter columns. But this is a 100 tons part and 52 meters high column (both parts)-
As always, I will appreciate your comments.
Regards
Luis
I have to deal with the job of joining the upper part of a heavy vessel by welding and PWHT.
I have reclaim the construction company, the procedure to suport this upper part during heat treatment.
This upper part is 60 mm- SA 516 70 carbon steel plate
Their answer, was to hold it with a crane (600 tons.). I have refused this procedure for holding the part, due to lack o plumbness and relative movements that induce cracks during the process.
I have already done this job in shorter and lighter columns. But this is a 100 tons part and 52 meters high column (both parts)-
As always, I will appreciate your comments.
Regards
Luis