ajk1
Structural
- Apr 22, 2011
- 1,791
We want to bond a new structural reinforced topping to an existing concrete floor slab so that the composite slab can support 250 psf live load. We are using a water based epoxy bonding agent with a 24 hour window. We have used this product on a number if projects and generally get 2 MPa (290 psi) bond strength.
Questions
1. How would you roughen to 5 mm amplitude an existing floor slab surface surrounding a column, where the shotblast machine cannot reach?
2. Are there smaller shotblast machines that can get closer to the column?
3. How close can they get?
4. I expect bush hammering should not be used to achieve the 5 mm amplitude because it produces a "bruised layer". Do you agree that it should not be used.
5. Assuming that high pressure water blast would make too much of a mess, would a heavy sandblast be the way to go?
6. Would a needle gun produce a bruised layer?