Our contractor that is designing a tank concrete foundation is asking these questions. Can you help me guide where and how to obtain their specific request (see below)? We don't have report and not planning to hire a geotechnical company at this point but maybe take sample to a soil laboratory and analyze the soil if this is what it takes to get the foundation design.
1. Site specific geotechnical request:
a. soil bearing capacity for normal loading and transient conditions
b. modulus of sub-grade reaction
c. matt foundation depth
d. lateral friction factor
e. backfill and its compaction requirement.
f. Settlement prediction for uniform, differential, short and long term.
1. Site specific geotechnical request:
a. soil bearing capacity for normal loading and transient conditions
b. modulus of sub-grade reaction
c. matt foundation depth
d. lateral friction factor
e. backfill and its compaction requirement.
f. Settlement prediction for uniform, differential, short and long term.