neaveyoung
Structural
- Jul 21, 2008
- 23
Recently i'm doing a calculation involved the cantilever sheet pile for temporary earth retaining structure. Actually my excavation depth is 2 meter and the embedment depth is 2.1 meter. I get the max. bending moment =42 kNm/m. Now my question is how to get the:-
1) Lateral deflection.
2) Adjacent ground settlement.
Thanks.
1) Lateral deflection.
2) Adjacent ground settlement.
Thanks.