jack36
Structural
- May 20, 2009
- 21
I have a 5-story hotel project coming up. Structural steel will be used up to the 2nd floor due to open 1st floor spaces, but we will go up from there with light gauge steel framing. My previous hotel work consisted of wood framing above the 2nd floor, so I would always use wood trusses for the floor system. I'm trying to decide if I will use light steel joists to frame the floors, or try to clear span between bearing walls with the steel deck. The deck would need to span 12'-9" between room walls. I have seen both systems and would like to get some feedback from those with experience on this.