bryson85
Structural
- Jan 29, 2007
- 3
The IBC states that a 50 plf be applied to the top rail of the guardrail. In a 3 span condition, I have seen it applied as a uniform load across the entire rail (3 spans) and I have seen it applied for just one span. Anybody have a comment on this? I know that a minimum 200 lb concentrated load is applied anywhere along the rail not concurrently with the uniform load.