skeletron
Structural
- Jan 30, 2019
- 885
I have a grouted masonry wall going up against a new concrete column. This is a repair, not a new build, so the two dissimilar materials are required. Column will be poured first, then the wall will be built up.
My question is:
Do you tie the masonry wall to the concrete column through horizontal post-installed bars? And if so, how do you determine how much steel needs to be there for restraint between the two dissimilar materials? Or, do you purposely let the joint float?
My concern is that:
A) They can't cast in the horizontal bars because of formwork and sequencing requirements
B) I'm looking at the proposed detail and it looks like they are tying in every 16" which makes me worried about chewing up the column and/or difficulty actually getting the bars to not hit the ties.
These seem more like prescriptive requirements revolving around typical .0015 or .002 ratios.
My question is:
Do you tie the masonry wall to the concrete column through horizontal post-installed bars? And if so, how do you determine how much steel needs to be there for restraint between the two dissimilar materials? Or, do you purposely let the joint float?
My concern is that:
A) They can't cast in the horizontal bars because of formwork and sequencing requirements
B) I'm looking at the proposed detail and it looks like they are tying in every 16" which makes me worried about chewing up the column and/or difficulty actually getting the bars to not hit the ties.
These seem more like prescriptive requirements revolving around typical .0015 or .002 ratios.