We've used them quite a bit - many good applications for them but some applications (per the above comments) might be not-so-good.
Historically helical piles started out using a single square bar of steel (1 1/2" sq) with cut and canted helical blades that formed the screw.
Recent years have seen more use of the pipe pile where a 2 7/8" dia. pipe with the helical blades is used.
I've used them mostly with underpinning work. Sometimes with new structures where traditional spread footings can't be designed to work - such as adjacent to an existing foundation.
I had a small, 9000 s.f. building that had sunk 9 inches at one end (due to poor grading and the presence of collapsible soils). We used the pipe piles - about 8 ft. on center around the perimeter grade beams and actually hydraulically jacked the whole building back into place - they were bolted onto the sides of the foundation walls. These weren't helical piling but actually "push piles" which were hydraulically jacked downward using the weight of the building.
Two ways to design/specify these things -
1. Prescriptive specification - the designer takes the soil data from a geotechnical report and uses helical pile design criteria to determine the number and diameter of helical plates as well as the estimated required depth. In the field ,the installer correlates the design to readings on the installation equipment that provides information on required torque.
2. Performance specification - the designer communicates with local helical pile suppliers and gets rough estimates of reasonable maximum pile capacities. Then the designer simply indicates on their plans the number, location, spacing, and required load capacity of piling. The helical pile supplier then provides piling that is certified to meet the required loads. During installation the pile capacity is determined from the torque required to install the piling.
A.B. Chance (
is a major supplier in our area of helical piling but check with your local firms. As you might guess, the performance specification is usually the best way to go - but again - depends on your local piling firms as to their preferences as well.