Hello,

one question again. I'm working on my first project with HEC-HMS. I got a example, but i want to understand what i'm done.
For a subbasin, you can choose the Baseflow Method Recession, like in my example. After this you have to enter a recession constant. Where can i get this figure or how i can compute this. I try it with google, but i'm from Germany and i didn't find a similar word.
The other possibility is, that i say, it's is only one rain event and the area is very small, so i don't need the baseflow.

thankful

larryTHUR
 