pjohnson
Civil/Environmental
- Jun 20, 2001
- 1
Our firm is interviewing for a contract with a local municipality that is looking for a "review" of their wastewater collection system. There have been several operational problems identified, but the main problems are due to poor engineering. It seems that the system built (1996) with very optomistic growth projections. There is approximatly eight miles of eight inch diameter force mains installed.
While I don't have much data at this point, an off the cuff estimate suggests that four inch diameter force mains would be sufficient for current flowrates, as well as reasonable growth projections. Their main complaint is odor in downstream lift stations.
The operators have tried injecting air into force mains to try to inhibit anerobic conditions, without much success, if any.
Does anyone have any suggestions as we prepare to interview for the contract to review the system and make reccomendations for improvements? How would you suggest that they deal with these oversize force mains, forever?
thanks,
pj
While I don't have much data at this point, an off the cuff estimate suggests that four inch diameter force mains would be sufficient for current flowrates, as well as reasonable growth projections. Their main complaint is odor in downstream lift stations.
The operators have tried injecting air into force mains to try to inhibit anerobic conditions, without much success, if any.
Does anyone have any suggestions as we prepare to interview for the contract to review the system and make reccomendations for improvements? How would you suggest that they deal with these oversize force mains, forever?
thanks,
pj