Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Grand opening delayed after brand new footbridge 'doesn't fit' 6

Status
Not open for further replies.

bimr

Civil/Environmental
Feb 25, 2003
9,321
 
Replies continue below

Recommended for you

Looks more like they were given the wrong measurement from historical plans. Perhaps they need to follow this rule, "measure at least once".

Keith Cress
kcress -
 
"The bridge doesn't fit," said Thomas Grün, the mayor of Bürgstadt in the state of Bavaria, turning to a group of kindergarten children.

The children, who were waiting to test out new pedestrian and biking bridge over the river Erft, consoled the mayor — telling him that at home, their building block play projects sometimes don't work either, reported the local Main-Echo newspaper Friday, recounting Thursday's aborted installation.
 
Apparently checking field measuremets was not within the fabricator's scope of work. {?}
"Field verify all measurements." is the first note on my drawings.


 
Status
Not open for further replies.

Part and Inventory Search

Sponsor