Pasted below (in no particular order) are some relevant comments posted to my PipingDesign group from February this year. I'm not sure if this addition will help.
The group is a closed, email-based list, so I can't just post a URL.
Paul
=======================================================
Hi Guy's,
with regard to the 'Golden Weld' theories
going around, the latest bit of info is that such
welds are now called 'Closure Welds' as the old term
is not representative, in this technically correct
world of today.
Anyway, being an 'old bod' I will stick to the term
for the sake of continuity.
In my experience with Golden Welds is that they were
always treated with the utmost repect for the obvious
reason, that they were not proof tested by going
through the hydrotest process.
As for the substitue measures that can be taken with
such welds, there are many and usually there is a
method statement generated and approved by the Client
to spell out the process for completing such welds.
I have in the past been involved with the witnessing
of such welds and it is usually up to the Welding
Engineer to decide on what length to go with these
joints, in the past I have had to follow a whole
variety of stringent controls to ensure that the welds
were carried out in the best possible way.
Some of the measures are as follows:
1). A qualified Inspector being present throughout the
welding operation to confirm the visual condition of
the weld at all stages of completion.
2). A visual inspection of the root of the weld, this
was achieved by leaving the final length of root bead
open, (100mm), for a visual inspection with a pen
light, to ensure defects such as lack of root fusion
were not present.
3). Controlled sequential welding was applied to
lessen the unnecessary stress that could be put into
the weld by not applying such method.
4). The Hot Pass of the weld was sometimes MPI'd or
DPI'd, dependant on the pre-heat requirements or the
material being welded.(never the root as it is too
sensitive an area and it is best to be covered over
with the hot pass bead as quickly as possible for
added strength).
5). Heat inputs were sometimes taken at certain
intervals during welding by the Inspector, as would be
during a Weld Procedure Qualification test, using
'Tong testers'/stopwatch/tape measure/calculator, to
ensure that the welder was working within the
peramaters stipulated in the relevant welding
procedure.
6). Joint interpass temperatures would be taken with a
digital thermometer at the end of each pass, to ensure
that the interpass tempareture was in line with the
welding procedure tolerances.
7). Finally, when the 'Golden Weld' was completed
there would be a whole range of NDE to complete such
as Visual inspection, MPI or DPI, Radiographic AND
Ultrasonic Inspection, both prior to and after Post
Weld Heat Treatment, (if PWHT was applicable).
Still being in the business after 35 years, I look in
dispair today when it is notedthat such critical
joints are not treated with the same respect today.
It is in my book better to be safe than sorry by going
the extra yard with the controls, in such critical
instances.
=======================================================
Speaking from the Inspector standpoint, I might only add one thing.
The processes for treating final closure welds are well spelled out
in some construction codes which I would consult for strict
compliance purposes. For instance, ASME B31.3 has extensive
directions which I have seen often change the decision on whether or
not to hydrotest when it is at all possible. As for the golden
term...I learn something new everyday!
=======================================================
In a new piping fabrication/installation/replacement jobs, generally all
the weld joints are hydroteted (along with other NDT methods) in phases.
However, sometimes due to some layout/site problems, it is almost impossible
to do hydrotest of the final weld joint. We refer that weld joint as golden
joint.
Generally, Dye penetrant test of root weld, radiographt etc.. is used for
quality control of that joint
Say, something like a hook-up to an existing line etc..
=======================================================
Golden weld means, InA tie-in work whatever joints were welded at the
fabrication shop,Balance weld must be only one joint at site
welding.This weldind joint cal be called as golden joint.This joints
should be 100% confidence with the all NDT.Welder could be very very
experienced man.
=======================================================
This must be the modern day replacement for the fabled golden rivet from
shipbuilding days. When inspecting a golden weld be sure not to bend over.