enggpiping
Mechanical
- Jun 20, 2007
- 6
Hello All,
I am about to provide an input to civil guys to design a sleeper for a bunch of NG lines & the smallest of which is 20" SCH 80 pipe.
This is inside process plant scenario so ASME B 31.3 is applicable.
I want to know the general way of calculating a pipe support span for a gas service line which will be hydro tested.
WRT the ASME B 31.3 it is mentioned that “345.3.2 Temporary supports. Piping designed for vapor or gas shall be provided with additional temporary supports, if necessary, to support the weight of test liquid."
So how do you guys calculate the support span in this situation?
Option 1)- Is it good to design the sleeper for gas filled spans however the provision for temporary hydro test supports are to be taken care for Hydro test before testing & removed after the test (is it very complicated? or it is a normal practice?)
Or Option 2)- It is better to Design the sleeper for liquid filled spans even if the regular line service is gas? Considering temporary supporting arrangement is way problematic at site & can increase complications?
Looking forward to your inputs on this at the earliest as the civil guy is behind me to get the concerned spans.
Thanks in advance
Regards,
Abhijit
Plant Layouts
I am about to provide an input to civil guys to design a sleeper for a bunch of NG lines & the smallest of which is 20" SCH 80 pipe.
This is inside process plant scenario so ASME B 31.3 is applicable.
I want to know the general way of calculating a pipe support span for a gas service line which will be hydro tested.
WRT the ASME B 31.3 it is mentioned that “345.3.2 Temporary supports. Piping designed for vapor or gas shall be provided with additional temporary supports, if necessary, to support the weight of test liquid."
So how do you guys calculate the support span in this situation?
Option 1)- Is it good to design the sleeper for gas filled spans however the provision for temporary hydro test supports are to be taken care for Hydro test before testing & removed after the test (is it very complicated? or it is a normal practice?)
Or Option 2)- It is better to Design the sleeper for liquid filled spans even if the regular line service is gas? Considering temporary supporting arrangement is way problematic at site & can increase complications?
Looking forward to your inputs on this at the earliest as the civil guy is behind me to get the concerned spans.
Thanks in advance
Regards,
Abhijit
Plant Layouts