connect2
Structural
- Dec 24, 2003
- 306
When you size a foundation for settlement, do you use all or a percentage of variable and or transitory loads such as wind, snow, and even live load? Do you do this based on cohesionless soils, almost immediate settlement vs. cohesive soils, settlements taking numbers of years with creep occurring over a decade type time scale never minding changes in pore water pressure. So this question is the same whether LFRD or WSD...settlement. What would be your opinion of this combined with also the use of live load reduction based tributary area? Might have been better to have posted in a different forum but it deals with the demand side of the equation so there you go. Thanks.